Michelle Dineley, CA
Installation
Sales- Brice
Turn- N/A
4TON upflow Goodman furnace, Honeywell #T6, 1" filter base.
Total due - $5,500.00 *Check*
- Date Ranges
- Date Ranges: 2025 - Q4
- Plumbing
- Price Ranges
- Price Ranges: -10000
Sam Ostrom, CA
Sales-Jimmy Conejo home services will open up section of drywall 10 to 12 feet in kitchen area to gain access to original cast-iron material that has a fracture all the way down vertical pipe.
Once removed we will install scheduled 40 PVC material from upstairs fixtures to footing downstairs in kitchen.
After scope of work has been performed, we will screw back sections of drywall that were removed, but cannot be held responsible for any type of painting, patching or texture to walls.
Job includes a five-year warranty on repair
Finance $3500.00
- Date Ranges
- Date Ranges: 2025 - Q4
- Plumbing
- Plumbing: Plumbing Install
- Price Ranges
- Price Ranges: -10000
Karen Levine, CA
Installation
Sales- Greg
Turn- Dan & George (Split)
D/S - 3TON upflow GR9S80 furnace/coil, Innovair 16-seer BOX A/C, NUVE Mid/Main Level- 4TON upflow GR9S80 furnace/coil, Innovair 16-seer BOX A/C, NUVE
U/S- 2TON horizontal GR9S80 furnace/coil, Innovair 16-seer BOX A/C, NUVE
Total due - $40,300.00 *ACCT TO CALL ON MONDAY FOR PAYMENT*
- Date Ranges
- Date Ranges: 2025 - Q4
- Plumbing
- Price Ranges
- Price Ranges: 40001 - 45000
Patrica Della Corna, CA
Almost done removing tiles and paper should be done by 11:00 tomorrow for there 12:00 inspection. There are some concerns around the turret they had problems there before we might want to do torch down in this area to prevent further leaking.
The guys are working on putting down paper/felt
Guy have back and sides finished working on front lower section
Nixon is here working on the torch down around the Turret the rest of the tile is almost finished they said they should be done by tomorrow.
- Date Ranges
- Date Ranges: 2025 - Q4
- Plumbing
- Price Ranges
- Price Ranges: 35001 - 40000
Ryan Allen, CA
Installation
Sales- Greg
Turn- Nathan
3TON horizontal/downflow GR9S80 furnace, ducting 4 runs, NUVE thermostat.
Total due - $13,150.00 (COLLECT CC)
- Date Ranges
- Date Ranges: 2025 - Q4
- Insulation
- Price Ranges
- Price Ranges: 10000 - 15000