Jeff/Linda Pohlman - $39500 - 12/9/22, CA
Install **PRE 7AM **USING (2) BOVB18'S, (1) 4-TON R802VA, AND (1)5-TON R802VA FROM CVHA-SHOP. PLEASE MAKE SURE TO GET MODELS/AND SERIALS SO CANDICE CAN REGISTER!!!
Sales- Greg
Turn- Georgie
Main House - 5TON/100K BTU Upflow R802VA furnace, coil, BOVB18 A/C
Bedrooms System- 4TON/80K BTU Horizontal R802VA furnace, coil, BOVB18 A/C$35,350.00 *Synchrony 18 months no interest*COLLECT $4,150.00
Total - $39,500.00
- HVAC
- HVAC: HVAC Install
- Price Ranges
- Price Ranges: 35001 - 40000
- Date Ranges
- Date Ranges: 2022 - Q4
Guenter Pauly - $7500 - 7/21/25, CA
Installation
Sales- Greg
Turn- Parker
D/S 4ton XR14 AC only
Deposit - $700.00 (check)
Total due - $6,300.00 (check)
Installation **NO PRE PERFORMED.
Sales- Greg
Turn- ParkerU/S - 3 OR 4TON BOVA15 A/C
Total due - $7,500.00 (CC or check)
- HVAC
- HVAC: HVAC Install
- Price Ranges
- Price Ranges: -10000
- Date Ranges
- Date Ranges: 2025 - Q3
- Date Ranges: 2023 - Q2
Arlene Olsen - $19200 - 3/25/24, CA
Installation
Sales- Greg
Turn- N/A
Duct cleaning 8 runs
Total due - $1,040.00
Install
Sales- Greg
Turn- N/A
3TON upflow R802VA furnace/coil, BOVB18 A/C, Honeywell #T6
Total due - $19,200.00 (Sync 0% / 18 Mos)**Furnace/coil were removed for MHS to remediate platform.
- HVAC
- HVAC: HVAC Install
- Price Ranges
- Price Ranges: 15001 - 20000
- Date Ranges
- Date Ranges: 2024 - Q1
- Price Ranges: -10000
- Date Ranges: 2024 - Q2
Ritch Mitchell - $10390 - 11/15/23, CA
Installation
Sales- Brice
Turn- Eric
3TON R95 horizontal furnace.
Total due - $10,390.00 (Collect CC)
- HVAC
- HVAC: HVAC Install
- Price Ranges
- Price Ranges: 10000 - 15000
- Date Ranges
- Date Ranges: 2023 - Q4
Florence Lafemina - $1266.8 - 3/24/25, CA
Installation **TWO DAY PROJECT 1/3 + 1/4 (insulation being performed on 1/4)
Sales- Jesse
Turn- Eric
HVAC - Upflow SL280V furnace, coil, BOVA15 A/C, ducting 7 supplies/3 returns/12 registers, Honeywell #T6INSULATION (1/4) Installing approx. 1,101 sw. ft. of blow-in insulation to R38 value over existing.
Total due - $24,510.00 *Financing; Service Finance*
Sales: Kevin 2 of 2Will need to shut down water supply to house, remove old emergency valves and supply lines, clean and prep work area, install new quarter turn emergency valves with new supply lines, energized water supply, preform a leak free inspection, cleanup work area.Will need to shut down gas meter supply, remove fittings and nipples and reseal threads with new fittings and new nipples, energize gas supply and preform a leak free inspection.
Due to age of water heater, it is possible that when turning off gas that there could be a problem with water heater not re lighting and may have to replace thermocouple and or replace water heater itself Collect: $ 1,266.80
Confirmed with Florence 805-990-1065 who will be on site 03/24
Sales: Kevin 1 of 2Will need to shut down water supply to house and replace shut off valve, drain water heater and remove old rotted wood stand, build and install new metal stand, build and install new 50 gal water heater up to plumbing code standards, energize water supply to house and preform a leak free inspection on all completed work, cleanup work area and haul away trash and old heater.
Collect: $3,485.00
Confirmed with Florence 805-990-1065 who will be on site 03/24
Install 1" regulator and laundry bib
Sold by Art
**UPON COMPLETION, PLEASE COLLECT $1,117.26**
Please call when on the way 805-990-1065
- Plumbing
- Plumbing: Plumbing Install
- Price Ranges
- Price Ranges: -10000
- Date Ranges
- Date Ranges: 2025 - Q1
- HVAC
- HVAC: HVAC Install
- Date Ranges: 2023 - Q3
- Plumbing: Water Heater Install
- Price Ranges: 20001 - 25000
- Date Ranges: 2024 - Q1
Customer Testimonials
There are no testimonials at this time. Check back later!